The National Grid Corporation of the Philippines (NGCP) and electric distribution utility provider MORE Power have announced of scheduled power interruptions in August 2024.

As NGCP will carry out scheduled maintenance work in August, MORE Power will take the opportunity to conduct repair of its facilities in areas affected by the power outage.

Here are the details of the scheduled power interruptions: 

August 4, 2024 (NGCP’s scheduled power interruption)

6 a.m. - 6 p.m. (12 hours)

Molo Substation

Diversion Substation

Megaworld Substation

Mobile Substation

 

August 10, 2024 (MORE Power’s scheduled power interruption)

6 a.m. - 12 noon (6 hours)

Portion of La Paz Feeder 1, along Jalandoni-Sinikway, Lapuz

 

August 11, 2024 (NGCP’s scheduled power interruption)

6 a.m. - 6 p.m. (12 hours)

Mandurriao Substation

Jaro Substation

 

August 18, 2024 (MORE Power’s scheduled power interruption)

5 a.m. - 8 a.m. (3 hours)

La Paz Substation

 

5 a.m. - 3 p.m. (10 hours)

La Paz Feeder 3 & 5 (along Jereos St. and Rizal St.)