Several transmission lines unavailable due to Tisoy —NGCP
By TED CORDERO, GMA News
Several power transmissions and distribution utilities went down as Typhoon Tisoy ravaged the Bicol region, the National Grid Corporation of the Philippines said Tuesday.
According to the NGCP, the following transmission lines are unavailable:
South Luzon
- Batangas-Taysan 69kV Line
- Customer Affected: MERALCO, FBPC
- Date/Time out: 3 December 2019 / 09:18AM
- Batangas-Mabini 69kV Line 1
- Customer Affected: BATELEC II
- Date/Time out: 3 December 2019 / 07:03AM
- Lumban-Famy 69kV Line
- Customer Affected: FLECO, QUEZELCO II
- Date/Time out: 3 December 2019 / 06:51AM
- Gumaca-Atimonan 69kV Line
- Customer Affected: QUEZELCO I
- Date/Time out: 3 December 2019 / 05:17AM
- Pitogo-Mulanay 69kV Line
- Customer Affected: QUEZELCO I
- Date/Time out: 2 December 2019 / 7:19PM
- Gumaca-Lopez 69kV Line
- Customer Affected: QUEZELCO I
- Date/Time out: 3 December 2019 / 12:36AM
- Naga-Iriga 69kV Line
- Customer Affected: CASURECO III
- Date/Time out: 2 December 2019 / 10:33PM
- Naga-Concepcion 69kV Line
- Customer Affected: CASURECO II
- Date/Time out: 2 December 2019 / 10:23PM
- Naga-Sto. Domingo 69kV Line
- Customer Affected: APEC
- Date/Time out: 2 December 2019 / 9:39PM
- Naga-Tinambac 69kV Line
- Customer Affected: CASURECO II
- Date/Time out: 2 December 2019 / 9:48PM
- Daraga-Legazpi 69kV Line
- Customer Affected: APEC
- Date/Time out: 2 December 2019 / 9:21PM
- Sorsogon-Bulan 69kV Line
- Customer affected: SORECO I
- Date/Time out: 2 December 2019 / 1:56PM
- Daraga-Ligao 69kV Line
- Customer affected: APEC
- Date/time out: 2 December 2019 / 6:21PM
Visayas
- Calbayog-Bliss 69kV Line
- Customer Affected: SAMELCO I
- Date/Time out: 2 December 2019 / 4:41PM
- Palanas-Cara-Catarman-Allen-Lao-ang 69kV Line
- Customer affected: NORSAMELCO
- Date/Time out: 2 December 2019 / 2:58PM
- Paranas-Taft-Borongan-Quinapondan 69kV Line
- Customer affected: ESAMELCO
- Date/Time out: 2 December 2019 / 2:27PM
- Calbayog-Palanas-Cara 69kV Line
- Customer affected: SAMELCO I
- Date/time out: 2 December 2019 / 3:01PM
- Ormoc-San Isidro 69kV Line
- Customer affected: LEYECO V, BILECO
- Date/time out: 2 December 2019 / 6:00 PM
- Date/time restored: 3 December 2019 / 12:16AM (partially restored)
"There are also 13 230kV transmission lines unavailable, affecting transmission services in Camarines Norte, Camarines Sur, Albay, and Sorsogon," the NGCP said.
Inspection and restoration of lines in the affected areas will be in full swing as soon as the weather allows, the power grid operator said. — BM, GMA News